Which airports in 2024 will receive funds from a controversial infrastructure bill? Worth as much as $1.5 trillion in total, the bill in question was signed into law as the Infrastructure Investment and Jobs Act by Joseph R. Biden — who is the current president of the United States — on Monday, November 15, 2021; and among the beneficiaries of the first $968,625,660.00 in funds are 85 airports throughout the country…
Interactive Lists: Which Airports In 2024 Will Receive Funds From Infrastructure Bill?
…but which 118 airports are receiving their share of the initial funds of the Airport Terminals Program — and which of the 118 airports will gain the most financially?
The bipartisan infrastructure law will help airports, according to the official Internet web site of The White House of the United States:
This will improve U.S. competitiveness, create more and better jobs at these hubs, and reduce emissions. Decades of neglect and underinvestment in our infrastructure have left the links in our goods movement supply chains struggling to keep up with our strong economic recovery from the pandemic. The Bipartisan Infrastructure Law will make the fundamental changes that are long overdue for our nation’s ports and airports so this will not happen again. The United States built modern aviation, but our airports lag far behind our competitors. According to some rankings, no U.S. airports rank in the top 25 of airports worldwide. Our ports and waterways need repair and reimagination too. The legislation invests $17 billion in port infrastructure and waterways and $25 billion in airports to address repair and maintenance backlogs, reduce congestion and emissions near ports and airports, and drive electrification and other low-carbon technologies. Modern, resilient, and sustainable port, airport, and freight infrastructure will strengthen our supply chains and support U.S. competitiveness by removing bottlenecks and expediting commerce and reduce the environmental impact on neighboring communities.
“Through the Bipartisan Infrastructure Law, a total of $5 billion has been allocated ($1 billion annually from 2022-2026) to provide competitive grants for airport terminal development projects that address the aging infrastructure of the nation’s airports”, according to this official article from the Federal Aviation Administration of the United States. “These grants will fund safe, sustainable and accessible airport terminals, on-airport rail access projects and airport-owned airport traffic control towers. Projects may also include multimodal development”
Interactive List of 118 Airports Which Were Approved For Funding 2024
An interactive list of the 85 airports which will receive financial aid from the third round of funding for the Airport Terminals Program from the bipartisan infrastructure law was custom created for your convenience.
STATE | CITY | AIRPORT NAME | AIRPORT LOCID | REGIONAL — PROJECT DESCRIPTION | FINAL APPROVED AMOUNT |
---|---|---|---|---|---|
Alaska | Anchorage | Ted Stevens Anchorage International Airport | ANC | This award funds the installation of 110 audio and visual monitors/stations in the terminal to better serve the passengers. | $1,520,000 |
Alaska | Anchorage | Ted Stevens Anchorage International Airport | ANC | This award funds the installation of a new passenger boarding bridge at gate B4. | $1,848,000 |
Alaska | Fairbanks | Fairbanks International Airport | FAI | This award funds the replacement of the passenger boarding bridge at Gate 3. | $2,375,000 |
Alaska | Ketchikan | Ketchikan International Airport | KTN | This award funds the terminal expansion for air taxi operations to include air taxi ticketing and holdroom space. The expansion will provide a separate terminal entrance for air taxi operations, thus creating greater access and isolating air taxi operations from the commercial operations and baggage claim entry and exits. | $2,000,000 |
Alaska | Sitka | Sitka Rocky Gutierrez | SIT | This award funds the remodeling of 17,900 sq. ft. and expansion of the terminal by 23,680 sq. ft., to include an additional passenger boarding bridge and increased baggage claim. | $2,151,303 |
Alabama | Gulf Shores | Gulf Shores International Airport ‐ Jack Edwards Field | JKA | This award partially funds the eligible portion of a new commercial service terminal to accommodate new air carrier service. | $5,000,000 |
Alabama | Huntsville | Huntsville Intl‐Carl T Jones Fld | HSV | This award funds the eligible portion of Phase 2 of the terminal and concourse renovations to include the expansion of the concourse for new ADA‐compliant restrooms, a new nursing room, new terminal escalators, and expansion of the terminal public area near the ticket counters. | $7,000,000 |
Arizona | Phoenix | Phoenix Sky Harbor International Airport | PHX | This award funds the replacement of chillers, condensing water pumps, central plant piping, heat exchangers and cooling towers, as part of the 30‐year‐old Central Utility Plant upgrade. | $36,000,000 |
Arizona | Yuma | Yuma International Airport | NYL | This award funds upgrading and replacing security cameras, access readers, fiber optics, data switches, and hardware at high security requirement locations to enhance security and aid in detecting potential threats against people, property, and aircraft at NYL. This project will link stand‐alone systems into a single platform and provide additional redundancy and resiliency. New equipment will promote energy efficiency and sustainability. | $950,000 |
California | Burbank | Bob Hope (Hollywood Burbank) Airport | BUR | This award funds the construction of portions of the foundational slab and structural components of the 355,000 sq ft Replacement Passenger Terminal (RPT) building at BUR. This will include portions of the Headhouse structure and 3 Concourse structures, all separated by seismic joints. | $17,300,000 |
California | Los Angeles | Los Angeles International | LAX | This award funds two areas of the Auxiliary Curbs at ITF West and ITF East which includes a combination of new, extending, widening, and utility improvements of surrounding roadways. | $31,000,000 |
California | Oakland | Metropolitan Oakland International Airport | OAK | This award funds Phase 1 of the restroom improvements including the reopening of a women's restroom at Gate 4, the renovation of the men's restroom at Gate 3, and the transformation of the existing men's Restroom at Gate 7 into single user all gender/family restrooms, accompanied by a dedicated lactation room. | $10,000,000 |
California | San Francisco | San Francisco International Airport | SFO | This award funds the replacement of critical mechanical and electrical components of the HVAC system at the International Terminal. Replacing these components will improve fire‐life safety compliance, reduce energy usage, reduce maintenance costs, and improve resilience. | $31,000,000 |
Colorado | Colorado Springs | Colorado Springs Airport | COS | This award funds a portion of the terminal renovations including holding areas, restrooms and public address system, improving ADA accessibility and increasing energy efficiency. | $6,000,000 |
Colorado | Denver | Centennial Airport | APA | This award funds a portion of a major renovation of the Airport Traffic Control Tower including the elevator, HVAC system, plumbing, electrical, exterior structure, and interior upgrades. | $8,000,000 |
Colorado | Denver | Denver International Airport | DEN | This award funds a portion of the baggage handling system replacement, including the control system. The new system will improve energy efficiency and increase capacity. | $26,600,000 |
Connecticut | New Haven | Tweed New Haven Airport | HVN | This award funds the design and permitting to construct a new 75,000 sq. ft. terminal building with six gates, an appropriately sized security screening area, new baggage handling systems, and holding room areas sized for the current and forecasted aircraft using the airport. The new terminal will replace the existing terminal complex that is significantly undersized and subject to frequent flooding. | $2,500,000 |
Connecticut | Windsor Locks | Bradley International Airport | BDL | This award funds the installation of mechanical systems associated with the 80,000 sq ft terminal expansion and renovating a portion of the existing terminal to accommodate installation of a new in‐line checked baggage inspection system. | $5,400,000 |
Delaware | Wilmington | Wilmington ‐ New Castle Airport | ILG | This award partially funds passenger terminal improvements including the expansion of the existing hold room and bathroom facility upgrades. | $5,600,000 |
Florida | Fort Lauderdale | Fort Lauderdale‐ Hollywood International Airport | FLL | This award partially funds a portion of the T1‐T2‐T3 Terminal Connector, which will complete post‐security connectivity between all terminals at the airport. The project consists of the construction of two connector walkways and modifications to the existing terminals including enhanced security checkpoints, a renovated bag hall, an expanded hold room, and additional retail space. | $50,000,000 |
Florida | Fort Myers | Southwest Florida International Airport | RSW | This award funds a portion of the reconfiguration and expansion of the terminal access and curbside roadways. | $8,000,000 |
Florida | Miami | Miami International Airport | MIA | This award funds the eligible portion of the rehabilitation of the airport's existing Automated People Mover (APM) connecting Lower Concourse E to the Concourse E‐Satellite. The project includes removal of the existing structure, utility and facility adjustments, and replacement of guideway system components. | $12,000,000 |
Florida | Miami | Miami International Airport | MIA | This award funds a portion of the design phase for the modernization and redevelopment of the airport's Central Terminal and Concourses E and F. | $15,000,000 |
Florida | Orlando | Orlando Sanford International Airport | SFB | This award funds a portion of the rehabilitation of the West Terminal corridor, increasing the passenger waiting area and ADA accommodations. | $1,000,000 |
Florida | Punta Gorda | Punta Gorda Airport | PGD | This award funds a portion of the terminal rehabilitation and expansion project, which includes renovating the security checkpoint and adding public circulation, hold rooms, and restroom space. | $10,000,000 |
Florida | St Petersburg‐Clearwater | St. Pete‐Clearwater International Airport | PIE | This award funds the eligible portion of the terminal renovation and expansion project, which consists of adding two new gates, consolidating TSA checkpoints, enlarging passenger hold rooms, increasing baggage make‐up capacity, and adding escalators and elevators. | $6,000,000 |
Florida | Titusville | Space Coast Regional Airport | TIX | This award partially funds the construction of a new Airport Traffic Control Tower. | $2,000,000 |
Florida | Venice | Venice Municipal Airport | VNC | This award funds the eligible portion of a new general aviation terminal building to meet existing and future demand. | $950,000 |
Florida | West Palm Beach | Palm Beach International Airport | PBI | This award funds a portion of Phase 2 of the Concourse B Expansion and Rehabilitation Project. This phase will complete the expansion and modernization of the 13‐gate concourse. | $7,000,000 |
Florida | Williston | Williston Municipal Airport | X60 | This award funds the eligible portion of a new general aviation terminal building to meet existing and future demand. | $500,000 |
Georgia | Atlanta | Hartsfield‐Jackson Atlanta International Airport | ATL | This award funds the rehabilitation and expansion of up to six public restrooms in the Central Passenger Terminal Complex. | $4,000,000 |
Georgia | Savannah | Savannah Hilton Head International Airport | SAV | This award partially funds the eligible portion of the structural elements for a four‐gate terminal expansion. | $5,000,000 |
Georgia | Valdosta | Valdosta Regional Airport | VLD | This award funds the eligible portion of the replacement of the Airport Traffic Control Tower. | $3,000,000 |
Georgia | Waynesboro | Burke County Airport | BXG | This award funds the eligible portion of a new general aviation terminal building to meet existing and future demand. | $750,000 |
Guam | Guam | Antonio B. Won Pat International Airport, Guam | GUM | This award funds the installation of a new terminal roof with a modern, energy efficient roofing system to strengthen resiliency, ensuring uninterrupted operations and passenger safety after natural disasters. | $21,400,000 |
Hawaii | Honolulu | Daniel K. Inouye International Airport | HNL | This award funds the rehabilitation of the Terminal 2 roadway for the movement of passengers on the “wiki wiki” bus, expanding passenger access (sidewalks), and lighting/electrical improvement to the Diamond Head (DH) Concourse. | $22,000,000 |
Hawaii | Kahului | Kahului Airport | OGG | This award funds the construction of a new two‐story security screening checkpoint facility at the south end of the ticket lobby, south TSA checkpoint. A pedestrian bridge will connect the new 6‐ lane screening checkpoint facility to hold room A and will span over the existing service road. | $8,600,000 |
Iowa | Des Moines | Des Moines International Airport | DSM | This award funds the vertical construction of common use terminal areas that incorporate elements to strengthen climate resilience, promote energy efficiency, and enhance accessibility. | $5,357,143 |
Idaho | Boise | Boise Airport | BOI | This award funds the remodel of approximately 383 sq. ft. of existing concourse secondary space into two multi‐use Gender‐ Neutral and Family Restrooms. | $1,000,000 |
Illinois | Cahokia/St Louis | Saint Louis Downtown Airport | CPS | This award funds the design to replace the existing terminal building. It includes the construction of a bus stop, which provides access to the Bi‐State Transit system and better meets the needs of airport users. | $450,000 |
Illinois | Chicago | Chicago O'Hare International Airport | ORD | This award funds improvements to Terminal 3 to include increasing the central passenger corridor width, a reconfigured TSA checkpoint, new hold room, a new ADA compliant family restroom, and updates to the baggage system. | $40,000,000 |
Illinois | Robinson | Crawford County Airport | RSV | This award funds construction of a new 6,300 sq. ft. ADA‐ compliant and climate change resilient terminal. | $3,800,000 |
Indiana | Huntingburg | Huntingburg Regional Airport | HNB | This award funds construction of a new General Aviation Terminal Building to replace a 60+ year old block structure. | $3,300,000 |
Kansas | Salina | Salina Regional Airport | SLN | This award funds the design and construction to expand the terminal, approximately 26,500 sq. ft., to include a new arrival/departure building and improvements to the existing building to provide additional ticket counter space, TSA passenger screening, restrooms, lobby area, and inbound/outbound area for checked bags. | $7,041,832 |
Kentucky | Louisville | Louisville Muhammad Ali International Airport | SDF | This award funds a portion of a microgrid system to improve the sustainability and resiliency of the airport's power systems. | $5,500,000 |
Kentucky | Louisville | Louisville Muhammad Ali International Airport | SDF | This award partially funds the Terminal A security screening expansion project, which consists of adding four screening lanes to the security checkpoint. | $7,500,000 |
Kentucky | Mount Sterling | Mount Sterling‐ Montgomery County Airport | IOB | This award funds the eligible portion of a new general aviation terminal building to meet existing and future demand. | $1,000,000 |
Louisiana | Galliano | South Lafourche Leonard Miller, Jr. Airport | GAO | This award funds approximately 40% of construction of eligible areas for the airport’s new terminal building, which is needed to meet existing demand and assure operational sustainability during and after climate related events. It will be constructed to hurricane resistant standards and include air service facilities, further enhancing operational resiliency. | $1,500,000 |
Louisiana | New Orleans | Louis Armstrong New Orleans International Airport | MSY | This award funds construction of the foundation for the North/South Connector Road’s north phase. The foundational piling operations will provide structural resiliency to withstand future climatic events, which have deteriorated the soil and created environmental concerns in past years. The new road will reduce emissions by directly connecting passengers between the airport’s North and South terminals and will link the terminals to the airport’s upcoming multimodal transit facility that will provide passenger rail service. | $7,000,000 |
Louisiana | Shreveport | Shreveport Regional Airport | SHV | This award funds the construction of approximately 5,000 sq. ft. of new terminal gate space in the existing mezzanine. The new floor space will expand passenger hold areas for gates one and eight, to accommodate recently up‐gauged aircraft. | $2,000,000 |
Massachusetts | Boston | General Edward Lawrence Logan International Airport | BOS | This award funds phase one of a two‐phase project to expand and renovate the existing Airport Traffic Control Tower. This phase includes the construction of new space to accommodate existing and new FAA equipment, technical operations, a flight simulator, and a contract weather observer. | $12,000,000 |
Maryland | Baltimore | Martin State Airport | MTN | This award partially funds a new Airport Traffic Control Tower that has reached the end of its useful life. | $5,400,000 |
Maryland | Baltimore | Baltimore Washington International Thurgood Marshall Airport | BWI | This award funds terminal building improvements, which replaces up to 14 passenger boarding bridges that have reached the end of their useful life. | $14,574,160 |
Maine | Eastport | Eastport Municipal Airport | EPM | This award funds the construction of a new terminal to replace the existing building which was removed in 2018. | $1,124,800 |
Maine | Portland | Portland International Jetport | PWM | This award funds installation of new passenger boarding bridges and fixed bridge extensions from the terminal building to serve multiple aircraft parked at numerous gates. The project also includes a new full gate concourse public restroom with adjacent gender‐neutral bathrooms, adult changing space, a pet relief area, and an expansion of the hold room. | $10,400,000 |
Maine | Presque Isle | Presque Isle International Airport | PQI | This award funds the early stages of the construction of a new larger terminal to replace the existing terminal. The phase includes construction of the superstructure and building enclosure. The new terminal will be ADA compliant, include appropriate life safety upgrades, and improve energy efficiency. | $6,500,000 |
Michigan | Hastings | Hastings City/Barry County Airport | 9D9 | This award funds reconstruction of the terminal building that was constructed in 1990 at the Hastings City/Barry County Airport. The airport performed a terminal planning study that was approved by the MDOT's Office of Aeronautics (block grant) on July 25, 2023. | $1,800,000 |
Minnesota | Bemidji | Bemidji Regional Airport | BJI | This award funds expansion of the passenger terminal building to address concerns with congestion and security. Improvements will better define and enclose the security checkpoint space for arriving passengers to separate them from passengers that have been screened and are waiting to board their flight. | $261,250 |
Minnesota | Duluth | Duluth International Airport | DLH | This award funds the relocation of an Airport Owned Airport Traffic Control Tower, a non‐standard tower commissioned in 1963. The project includes design, project formulation, site preparation, line of sight obstruction removal, and other related actions. | $10,000,000 |
Minnesota | Minneapolis | Minneapolis‐St. Paul International Airport | MSP | This award funds expansion of the terminal to include 2 new gates and related infrastructure at the north end of Terminal 2, H15 and H16. | $20,000,000 |
Minnesota | Two Harbors | Two Harbors Municipal Airport ‐ Helgeson Field | TWM | This award funds construction of a general aviation terminal to replace the existing 640 sq. ft. terminal originally constructed in 1976. | $1,140,000 |
Missouri | Kirksville | Kirksville Regional Airport | IRK | This award funds the construction of a replacement terminal, approximately 6,500 sq. ft. The new terminal will meet current design and accessibility standards and replaces current terminal that has reached the end of its useful life. | $3,200,000 |
Missouri | Springfield | Springfield‐Branson National Airport | SGF | This award funds the improvement of the passenger terminal building by replacing up to five passenger boarding bridges that have exceeded their useful life. | $5,357,143 |
MP | Rota Island | Rota International Airport | GRO | This award funds the replacement of the existing terminal roof (approx. 11,380 sq. ft.) including portions of the structural support elements (footings, columns, beams, slabs) and associated modifications. | $4,500,000 |
Mississippi | Jackson | Jackson‐Medgar Wiley Evers International Airport | JAN | This award partially funds a terminal rehabilitation consisting of replacing escalators, elevators, HVAC systems, generators, passenger boarding bridges, and baggage belts. | $8,000,000 |
Mississippi | Meridian | Meridian Regional Airport (Key Field) | MEI | This award funds a portion the eligible portion of a new terminal building and terminal access road. | $7,500,000 |
Montana | Kalispell | Glacier Park International Airport | GPI | This award funds a portion of the terminal expansion and modernization project, common‐use gate expansion, ticketing and kiosk areas, additional passenger hold rooms, and additional checkpoints and drive lanes. | $2,800,000 |
Montana | Missoula | Missoula Montana Airport | MSO | This award funds a portion of the new terminal construction, including the baggage claim, hold rooms, and passenger restroom areas. | $6,000,000 |
North Carolina | Charlotte | Charlotte Douglas International Airport | CLT | This award funds the replacement of up to 16 passenger boarding bridges and associated Ground Power Units and Pre‐Conditioned Air units. | $27,000,000 |
North Carolina | Raleigh/Durham | Raleigh‐Durham International Airport | RDU | This award funds a portion of the Terminal 2 security checkpoint, baggage claim, and Federal Inspection Station expansion. | $12,000,000 |
North Carolina | Spruce Pine | Avery County Airport | 7A8 | This award funds the eligible portion of the construction of a new general aviation terminal building to meet existing and future demand. | $2,000,000 |
North Carolina | Wilmington | New Hanover County Airport Authority dba Wilmington International Airport | ILM | This award funds a portion of the terminal access road and terminal curb front expansion and realignment. | $4,000,000 |
North Dakota | Fargo | Hector International Airport | FAR | This award funds a portion of the rehabilitation and expansion of the existing terminal. Rehabilitation includes upgrades to lighting, reconfiguration and expansion of hold rooms, and improve ADA compliance. Expansion includes four new gates for a total of nine, increasing hold room space and expanded ticketing/baggage handling, restrooms and post‐security concessions. | $10,000,000 |
North Dakota | Fort Yates | Standing Rock Airport | Y27 | This award funds construction of a new general aviation terminal building. | $700,000 |
Nebraska | North Platte | North Platte Regional Airport | LBF | This award funds the construction of a replacement terminal building, approximately 25,000 sq. ft., to meet demand and replace aging infrastructure. | $7,041,832 |
Nebraska | Omaha | Eppley Airfield | OMA | This award funds the Terminal Building Improvement, Phase 7, which will provide up to five new passenger boarding bridges as part of a multi‐year Terminal Modernization Project. | $3,148,251 |
New Hampshire | Concord | Concord Municipal Airport | CON | This award funds construction of a new terminal building and demolition of the existing terminal which is 84 years old and one‐ third of the size needed. | $2,510,000 |
New Mexico | Albuquerque | Albuquerque International Sunport | ABQ | This award funds the environmental review and design of a new in‐line baggage handling systems, hold rooms, and terminal interior and exterior space. The new in‐line systems will consolidate the existing eight systems into two more efficient ones, and consolidate hold space. | $5,800,000 |
New Mexico | Clovis | Clovis Regional Airport | CVN | This award funds approximately 35% of the design and construction costs of the total eligible costs of a new terminal building. The new 26,000 sq ft building will accommodate required interior space for TSA screening areas for passengers and baggage as well as gate areas, restrooms, and other facilities. | $3,500,000 |
Nevada | Reno | Reno‐Tahoe International Airport | RNO | This award funds the new Central Utility Plant (CUP). Specifically, this project includes chillers, heat exchangers, water pumps, cooling towers, water softeners and water treatment systems. | $7,000,000 |
New York | Albany | Albany International Airport | ALB | This award funds the rehabilitation, modification, improvement of Terminal A. The project will increase hold room capacity, accommodate up to two new passenger boarding bridges, improve the HVAC and electrical system, and add additional restrooms. | $10,600,000 |
New York | Buffalo | Buffalo Niagara International Airport | BUF | This award funds the replacement of up to 4 existing passenger boarding bridges, including new ground power units, and preconditioned air units. | $4,400,000 |
New York | Westhampton Beach | Francis S. Gabreski Airport | FOK | This award partially funds the construction of a new Airport Traffic Control Tower to replace the existing 1940's tower, which has exceeded its useful life and does not meet current standards. | $4,900,000 |
Ohio | Cleveland | Cleveland Hopkins International Airport | CLE | This award funds rehabilitation of the terminal building to include rehabilitating terminal wall surfaces, replacing tunnel ceiling, waterproofing the membrane in the tunnel tramway, performing structural repairs and installing new drainage system at the intermodal terminus of Greater Cleveland RTA's public rapid‐ transit rail service at the terminal. | $4,800,000 |
Ohio | Dayton | James M. Cox Dayton International Airport | DAY | This award funds the replacement of two existing passenger boarding bridges in Concourse B. | $2,900,000 |
Ohio | Gallipolis | Gallia‐Meigs Regional Airport | GAS | This award funds the reconstruction of the existing 1960s General Aviation Airport Terminal Building including interior and exterior improvements such as a new HVAC system, roof, windows, and doors. | $1,900,000 |
Ohio | Willoughby | Lake County Executive Airport | LNN | The award funds the replacement of the current 37‐year old trailer with a new terminal building. | $2,600,000 |
Oklahoma | Stillwater | Stillwater Regional Airport | SWO | This award funds approximately 20% of construction of eligible areas for the airport’s new terminal building. The new terminal will include larger gate hold areas for increased operational efficiency and capacity. | $4,500,000 |
Oklahoma | Tulsa | Tulsa International Airport | TUL | This award funds approximately 25% of the construction costs of a new replacement Airport Traffic Control Tower, which has three identified line of sight impediments and is not ADA compliant or accessible. Funding for this phase focuses on the vertical build construction. | $12,500,000 |
Oregon | Portland | Portland International Airport | PDX | This award funds the replacement of up to 9 passenger boarding bridges that have reached the end of their useful life. | $8,214,286 |
Oregon | Redmond | Redmond Municipal Airport | RDM | This award funds a portion of the terminal building expansion project, which will increase the building size to nearly double and improve energy efficiency and ADA compliance. | $7,000,000 |
Pennsylvania | Harrisburg | Harrisburg International Airport | MDT | This award funds the replacement of up to six existing passenger boarding bridges that are beyond their useful life. | $7,500,000 |
Pennsylvania | Lancaster | Lancaster Airport | LNS | This award funds passenger terminal improvements including expansion of the existing passenger screening and hold room areas. | $2,700,000 |
Pennsylvania | Philadelphia | Philadelphia International Airport | PHL | This award partially funds improvements under the Terminal Energy Optimization Program which includes HVAC and electrical efficiency upgrades and improvements. | $20,400,000 |
Pennsylvania | Pittsburgh | Pittsburgh International Airport (PIT) | PIT | This award funds a portion of the construction of a new 700,000 sq. ft. landside terminal building. | $5,300,000 |
Puerto Rico | Aguadilla | Rafael Hernandez Airport | BQN | This award funds a portion of a new terminal building departure hall, including four new gates. | $3,600,000 |
Puerto Rico | San Juan | Luis Muñoz Marín International Airport | SJU | This award partially funds the design and construction of a two mega‐watt photo‐voltaic array structure to supply sustainable and resilient power to Terminal A. | $5,000,000 |
South Carolina | Hilton Head Island | Hilton Head Island Airport | HXD | This award funds a portion of the final phase of the terminal expansion and renovation, which includes renovation of the aging terminal and increasing capacity with a new customer ticketing area, expanded baggage claim, outbound bag make up area, new restrooms, and improved passenger circulation. | $5,000,000 |
South Carolina | Myrtle Beach | Myrtle Beach International Airport | MYR | This award funds the structural elements of the Concourse A expansion project, which is a two‐level, six‐gate expansion to meet existing and future demand. | $10,000,000 |
South Dakota | Spearfish | Black Hills Airport ‐ Clyde Ice Field | SPF | This award funds the construction of a 3,300 sq. ft. General Aviation Terminal to replace the current 50‐year‐old building. | $1,950,000 |
Tennessee | Bristol/Johnson/Kingsport | Tri‐Cities Airport Authority | TRI | This award funds the eligible portion of the design of the Terminal Concourse Connector rehabilitation project, which will expand the width of the corridor and improve associated building infrastructure systems to accommodate current and projected passenger volumes. | $765,000 |
Tennessee | Nashville | Nashville International Airport | BNA | This award funds a portion of the lengthening and widening of the Terminal Access and Circulation Road from three to six lanes. | $5,000,000 |
Texas | Austin | Austin‐Bergstrom International Airport | AUS | This award funds the design of the airport’s new 20 gate midfield concourse B and related infrastructure. The project is a significant enabling component and early phase of Austin’s Airport Expansion and Development Program. | $14,250,000 |
Texas | Austin | Austin‐Bergstrom International Airport | AUS | This award funds the infill of the current terminal’s atrium with a concrete slab on the ticketing/concourse level adding approximately 13,000 sq. ft., which will accommodate more passengers transiting through the terminal. | $25,260,000 |
Texas | Dallas‐Fort Worth | Dallas Fort Worth International Airport | DFW | This award funds the reconstruction and modernization of at least 20 of the airport’s 34 existing airside restroom facilities. | $11,000,000 |
Texas | Harlingen | Valley International Airport | HRL | This award funds approximately 25% of the construction costs of a new sponsor owned FAA Contract Tower, which has an identified line of sight impediment. The existing tower is not ADA compliant and has structural integrity issues. The funding for this phase focuses on the foundation and base of the tower construction. | $4,500,000 |
Texas | Houston | George Bush Intercontinental Airport | IAH | This award funds the expansion, reconstruction, and modernization of at least 10 existing airside restroom facilities in Terminals A and D. | $5,490,000 |
Texas | Killeen | Skylark Field Airport | ILE | This award funds approximately 50% of the final phase of construction of eligible areas for the airport’s new terminal building. | $1,500,000 |
Texas | Lubbock | Lubbock Preston Smith International Airport | LBB | This award funds approximately 70% of the design and construction costs to replace and modernize the terminal building’s HVAC and associated systems including HVAC units, chillers, and related systems, and 11 air handling units. | $5,700,000 |
Texas | Midland | Midland International Air & Space Port | MAF | This award funds approximately 70% of the design for the replacement and modernize of the terminal building’s HVAC and related systems, restrooms, and passenger screening areas. | $2,800,000 |
Texas | San Antonio | Kelly Field Airport at Port San Antonio | SKF | This award funds approximately 10% of construction of eligible areas for the airport’s new terminal building. This phase will focus on the foundation and exterior construction. | $3,000,000 |
Texas | San Antonio | San Antonio International Airport | SAT | This award funds the environmental review and partial design of a new terminal connector and associated enabling projects for the new Terminal C. The connector will provide access between the two existing terminals, enabling passengers to move between them without having to exit the secure area and re‐enter. | $18,000,000 |
Utah | Salt Lake City | Salt Lake City International Airport | SLC | This award funds a portion of the Concourse B expansion that will include 16 gates and permanent hardstands. This expansion will allow for increased flight capacity and access for new entrants. | $20,000,000 |
Virginia | Norfolk | Norfolk International Airport | ORF | This award will partially fund the construction of a new Federal Inspection Service facility to meet the U.S. Customs and Border Protection requirements. | $6,000,000 |
Virginia | Washington | Washington Dulles International Airport | IAD | This award partially funds the 14 gate, 400,000 sq. ft. terminal building including direct connections to the Aerotrain and indirect connection to the Metrorail. | $35,000,000 |
Washington | Seattle | Seattle‐Tacoma International Airport | SEA | This award funds a portion of the widening of the arrivals terminal access road by two lanes including realignment of the departures access road and associated infrastructure. | $10,400,000 |
Washington | Spokane | Spokane International Airport | GEG | This award funds up to two additional ticket counters and passenger boarding bridges, and portions of the HVAC, mechanical, electrical, plumbing upgrades, shared‐use & hearing impaired technology, smart glass, solar energy connection, baggage handling systems and considerable ADA improvements. | $2,000,000 |
Wisconsin | Appleton | Appleton International Airport | ATW | This award funds the expansion and modernization project that includes a 4‐gate concourse expansion and will include a 60,000 sq. ft. expansion increasing the number of gates to 10. This award will partially fund the final phase of the concourse expansion project, including passenger boarding bridges, a solar and sustainability program, and mechanical equipment. | $3,420,000 |
STATE | CITY | AIRPORT NAME | AIRPORT LOCID | REGIONAL — PROJECT DESCRIPTION | FINAL APPROVED AMOUNT |
The ten international airports which serve the greater metropolitan areas of the cities were approved of the most funds for 2024 in the following order:
- Fort Lauderdale — 50 million dollars
- Chicago — 40 million dollars
- Phoenix — 36 million dollars
- Washington Dulles — 35 million dollars
- Los Angeles — 31 million dollars
- San Francisco — 31 million dollars
- Charlotte — 27 million dollars
- Denver — 26.6 million dollars
- Austin – 25.26 million dollars
- Honolulu — 22 million dollars
Interactive List of 104 Airports Which Were Approved For Funding 2023
An interactive list of the 104 airports which have been approved for financial aid from the second round of funding for the Airport Terminals Program from the bipartisan infrastructure law was custom created for your convenience.
STATE | CITY | AIRPORT NAME | AIRPORT LOCID | REGIONAL — PROJECT DESCRIPTION | FINAL APPROVED AMOUNT |
---|---|---|---|---|---|
Alaska | Anchorage | Ted Stevens Anchorage International Airport | ANC | The North Terminal passenger capacity is limited by the bag handling system. This project increases North Terminal capacity by installing common use equipment and upgrades the baggage handling system. | $4,400,000 |
Alabama | Fairhope | H.L. "Sonny" Callahan Airport | CQF | This award funds a portion of a project for the design and construction of a 4,148 square feet general aviation terminal building and associated site development on the east side of the airfield. | $2,000,000 |
Arkansas | Little Rock | Bill and Hillary Clinton National Airport | LIT | This award supports the second of four phases of the construction of a new 70,000 square feet Central Utility Plant (CUP). This phase completes the drainage and utility relocation, and the replacement of switchboards 1 and 2. | $8,000,000 |
Arkansas | Texarkana | Texarkana Regional Airport | TXK | This award will fund the final phase of construction for the new terminal building at the Texarkana Regional Airport. This award will provide funding to complete the exterior site work, which specifically includes accessible sidewalks, security fencing, concrete driveways, and impact rated bollards. | $4,275,000 |
Arizona | Yuma | Yuma International Airport | NYL | This project replaces the 20 year flooring with a continuous terrazzo system, to address ADA hazards, by removing existing transitions between various flooring types. | $1,100,000 |
California | Burbank | Bob Hope (Hollywood Burbank) Airport | BUR | This project will fund a portion of the construction of a new 355,000sf, 14‐gate terminal building replacing an outdated 1930's facility that is currently an airfield obstruction. The project will deliver a modern energy efficient facility that complies with FAA standards. | $30,000,000 |
California | Fresno | Fresno Yosemite International Airport | FAT | This project is funding a portion of the construction of a new terminal concourse including 2 new international/domestic gates with new hold rooms, new international arrivals center, and expanded passenger screening checkpoint. | $7,100,000 |
California | Los Angeles | Los Angeles International | LAX | The LAX Terminal Roadways Project will reconstruct and reconfigure the roadway system into LAX. This project will fund a portion of the design of the roadway system serving all existing and proposed terminals at LAX. | $31,000,000 |
California | Monterey | Monterey Peninsula Airport District | MRY | The relocated terminal complex is the fourth phase of MRY's Airport Safety Enhancement Program (SEP). The SEP will permit relocation of Taxiway A to meet FAA design standards. This project is for the design and Phase 1 construction of the replacement terminal. Phase 1 consists of enabling projects including the relocation of utilities and construction of a retaining wall to support the new terminal. | $3,000,000 |
California | Palm Springs | Palm Springs International Airport | PSP | The project will fund a portion of the expansion and renovation of the baggage claim including four new carousels and upgrades to flooring, electrical and ventilation systems. | $5,700,000 |
California | Sacramento | Sacramento International Airport | SMF | This project is funding a portion of the design and Phase 1 construction of an elevated, ADA‐compliant continuous pedestrian walkway and vertical structure connecting Terminal B and Concourse B as a secondary passenger conveyance system. | $11,700,000 |
California | San Diego | San Diego International Airport | SAN | This project will fund a portion of the construction of a new 1,210,000 SF terminal building with the addition of 30 gates. | $20,000,000 |
California | San Francisco International Airport | San Francisco International Airport | SFO | This project will fund a portion of the rehabilitation of SFO's International Terminal Building roofing system, including photovoltaic system upgrades, roof membrane and waterproofing system replacement, and removal of damaged exterior steel. | $31,000,000 |
Colorado | Colorado Springs | Colorado Springs Airport | COS | The Concourse Modernization is a complete remodel of the terminal concourse. This project funds a portion of the renovation including holding areas, restrooms and the Public Address system. It will improve ADA accessibility and increase energy efficiency. | $6,000,000 |
Colorado | Denver | Denver International Airport | DEN | This project funds a portion of the baggage handling system replacement, including the control system and curbside conveyors. The new system will improve energy efficiency and will increase capacity. | $22,000,000 |
Colorado | Englewood | Centennial Airport | APA | This project is for the design of a new Airport Traffic Control Tower replacing a nearly 40‐year old tower. The new tower will meet current building codes and ADA standards, will increase operational capacity, and will enhance airfield safety. | $4,000,000 |
Connecticut | Windsor Locks | Bradley International Airport | BDL | This award funds a portion of a terminal expansion project at the airport. This includes a new in‐line checked baggage system and control room, expanded passenger hold rooms, new airline gate space, and other modifications to for the efficient movement of passengers and baggage. | $5,000,000 |
Florida | Key West | Key West International Airport | EYW | This award funds a portion of a project to construct a new 48,800 square feet Concourse A immediately north of the existing airside terminal building. The new concourse will include 7 passenger boarding bridges. The project also includes about 20,000 square feet of renovations to the existing airside terminal building to expand the existing baggage claim and passenger security screening checkpoint. | $13,300,000 |
Florida | Melbourne | Melbourne Orlando International Airport | MLB | This award funds a portion of a terminal building rehabilitation and expansion. This includes expanding gates, and updating fire sprinkler system, plumbing, lighting, and flooring in the existing terminal. | $5,000,000 |
Florida | Orlando | Orlando International Airport | MCO | This award funds a portion of the Terminal C multi‐modal connector pedestrian bridge project, which will complete the construction of a 450‐foot enclosed pedestrian walkway. This walkway connects Terminal C with an adjacent multi‐ modal facility. | $20,000,000 |
Florida | Orlando | Orlando International Airport | MCO | This award funds a portion of the south terminal C phase 1 project. This project provides for construction of 4 additional multiple aircraft ramp system (MARS) gates which includes 8 loading bridges capable of serving either 4 wide‐body or 8 narrow‐ body aircraft. | $49,000,000 |
Florida | Sarasota | Sarasota Bradenton International Airport | SRQ | This award funds a portion of a terminal expansion project that adds five gates and associated holdrooms, new passenger security screening checkpoint lanes, and a new energy efficient Central Energy Plant. This phase of the project consists of completing the vertical construction package. | $10,000,000 |
Florida | Venice | Venice Municipal Airport | VNC | This award funds a portion of the design for the relocation and replacement of the existing outdated general aviation terminal building. The proposed new terminal will be a three story building of approximately 6,000 square feet, which will include the construction of sidewalks from Airport Avenue to the new terminal, and a new airport access roadway. | $300,000 |
Florida | Vero Beach | Vero Beach Regional Airport | VRB | This award funds the rehabilitation and expansion of the general aviation terminal. The project includes expanded security screening area, additional passenger seating, updated signage, and restroom and baggage pickup area improvements. | $1,000,000 |
Georgia | Augusta | Augusta Regional Airport | AGS | This award funds a portion of a project to rehabilitate the existing commercial passenger terminal building, adding an additional 1,420 square feet to the passenger holdroom. It will include new paint and flooring, new lighting, and new hold room seating. | $3,000,000 |
Georgia | Savannah | Savannah Airport Commission | SAV | The security screening checkpoint expansion project consists of adding 23,000 square feet to the south side of the terminal building. This award funds a portion of phase 2 of the project which includes relocating and expanding from four to six screening lanes. | $6,500,000 |
Hawaii | Kailua Kona | Ellison Onizuka Kona International Airport at Keahole | KOA | This project is for the replacement and upgrade of the airport Fire Alarm System to meet current standards. | $1,200,000 |
Iowa | Clear Lake | Mason City Municipal Airport | MCW | The Airport is building a new 23,000 square feet Airport Terminal with Bus Line facilities to replace an existing terminal. This project funds the passenger boarding bridge to enhance passenger accessibility and safety. | $1,215,000 |
Iowa | Des Moines | Des Moines International Airport | DSM | This project replaces the 1948 terminal that is beyond its useful life, capacity, and is non‐conforming with design standards. This project supports vertical construction of terminal, offering opportunities to strengthen climate resilience, promote energy efficiency, and create good paying jobs. This phase includes preparation and construction of the terminal foundation. | $10,800,000 |
Idaho | Idaho Falls | Idaho Falls Regional Airport | IDA | This award will fund a portion of a project to expand the ticketing, bag screening, hold rooms, passenger exiting, and restroom areas of the terminal. This project will update and consolidate the mechanical, electrical, and plumbing systems to substantially improve the energy efficiency and resiliency of the terminal. | $5,200,000 |
Illinois | Cahokia | Saint Louis Downtown Airport | CPS | This award funds a portion of a project to reconstruct the existing, inefficient, 1980 terminal building, which has met its useful life. The new modern terminal will meet current building codes including ADA compliance, be more energy efficient, and meet the current and future demand of the airport. | $2,500,000 |
Illinois | Chicago | Chicago O'Hare International Airport | ORD | This award funds a portion of a project to rehabilitate and expand the 60‐year‐old Terminal 3. This includes improvements to the central passenger corridor width, reconfigured TSA checkpoint, expanded holdroom, new ADA compliant restroom and a family restroom, and updates to the passenger baggage system. | $50,000,000 |
Illinois | Peoria | General Wayne A. Downing Peoria International Airport | PIA | This award funds the remaining portion of a project to replace the 63 year old airport owned airport traffic control tower with a new modern tower that meets FAA standards. | $14,010,000 |
Indiana | Fort Wayne | Fort Wayne International Airport | FWA | The Terminal Expansion and Modernization Program (Phases 1‐3) improves airfield safety through partial terminal relocation. This award funds a portion of the East Expansion Phase 3. This includes relocating four passenger boarding bridges to the second‐floor concourse, with adequate clearance from the taxiway. | $8,000,000 |
Kansas | Dodge City | Dodge City Regional Airport | DDC | The airport is expanding and rehabilitating the terminal buildings through a two‐ phase approach. This award will fund Phase 1 which includes updating the previous design, remove and expand the south portion and remodel the rest of the terminal building. The airfield vault, in the terminal basement, will also be moved to an enclosure outside the terminal under this project. | $7,300,000 |
Kentucky | Hebron | Cincinnati/Northern Kentucky International Airport | CVG | This award funds a portion of the design and replacement of up to 28 passenger boarding bridges on Concourse B. This includes the replacement of ground power units, pre‐conditioned air units and associated electrical, security, and access control systems. | $14,000,000 |
Kentucky | Lexington | BLUE GRASS AIRPORT | LEX | This award funds a portion of phase 1 of a project to replace and install two passenger boarding bridges. | $2,000,000 |
Louisiana | ‐ Kenner | Louis Armstrong New Orleans International Airport | MSY | This award funds a portion of the site preparation work and construction of a road between the north terminal and south campus parking and rental car facilities. This project enhance safety, reduce idling/carbon emissions, and connects the terminal to transit/passenger rail (part of a larger DOT multi‐modal community/airport project). | $8,000,000 |
Louisiana | Lake Charles | Chennault International Airport | CWF | This award funds the replacement of the exterior metal panel rain screen on the ATCT and will create resiliency as well as mitigate hazardous conditions resulting from the damaged screen, including electrical risks and environmental hazards. This upgrade will shield the base building from heavy rains, prevent water intrusions in storm conditions, and protect the tower's electrical, mechanical, elevator, and communication equipment. | $500,000 |
Louisiana | Pineville | Esler Regional Airport (ESF) | ESF | This award funds the replacement of the terminal HVAC system, roof, and windows. | $1,400,000 |
Massachusetts | Boston | General Edward Lawrence Logan International Airport | BOS | This award funds a portion of the ongoing $700M expansion of Terminal E. This award includes a new oversized baggage belt, an expanded arrivals curb, renovations to the arrivals level canopy and two new flex gate passenger boarding bridges. | $22,500,000 |
Maryland | Glen Burnie | Baltimore/Washington International Thurgood Marshall Airport | BWI | This project will fund a portion of the Concourse A and B expansion project which includes: baggage system improvements, direct airside connection between Concourses A and B, expanded apron level operations space, larger hold rooms, new concession space and modern restrooms. | $38,000,000 |
Maine | Oxford | Oxford County Regional Airport | 81B | This award funds a project to rehabilitate the existing General Aviation terminal building. The project is comprised of rehabilitation of the existing fire alarm system, heating system, emergency lights and signs, bathrooms, and other portions of the terminal. The project will also add solar panels on portions of the roof. The updated facility will meet current standards and ADA requirements, be more energy efficient, and meet the current and future passenger demand at the airport. | $243,825 |
Michigan | Detroit | Detroit Metropolitan Wayne County Airport | DTW | The Airport is replacing more than 100 passenger loading bridges over multiple years. This project funds a portion of the 34 terminal passenger loading bridges that have reached the end of their useful life. | $6,000,000 |
Michigan | Hillsdale | Hillsdale Municipal Airport | JYM | This award funds a project to replace the Airport's existing terminal facility with a new terminal located in a more accessible area. The new modern terminal will be more accessible including ADA compliant, meet current building code requirements, and be more energy efficient. | $2,500,000 |
Michigan | Traverse City | Cherry Capital Airport | TVC | This project will replace approximately 5 passenger boarding bridges that have outlived their useful life. | $5,225,000 |
Minnesota | Duluth | Sky Harbor Airport | DYT | This award funds a project to replace the existing 40‐year old 2‐story terminal with a new single story modern terminal. The new modern terminal will be ADA compliant, meet the City and DNR Regulatory Flood Protection Elevation, meet building code requirements, and have energy efficient features. | $1,187,000 |
Minnesota | Minneapolis | Minneapolis‐St. Paul International Airport | MSP | This award funds a portion of a project to rehabilitate and reconfigure Terminal 1 ‐ Concourse G between existing Gates G8 and G13 to add more passenger seating, new restrooms, and upgraded concessions space. | $10,000,000 |
Missouri | Clinton | Clinton Regional Airport | GLY | The existing terminal is located within the secure area of the airport and adjacent to two active taxiways. Anyone accessing the facility is required to walk across the active taxiways. This project reconstructs a replacement terminal building in a new location eliminating the need to cross taxiways. The project also includes the reconstruction of the airport entrance road. | $1,691,437 |
Missouri | Lee's Summit | Lee's Summit Municipal Airport | LXT | LXT seeks to relocate the terminal building to allow Runway 18/36 to Taxiway A to meet separation design standards. This project will fund the design for a relocation and construction of a new energy efficient and accessible terminal building to the east side of the airfield. | $570,000 |
Missouri | St. Joseph | Rosecrans Memorial Airport | STJ | The City of St. Joseph owns the existing airport traffic control tower. This project reconstructs the existing tower to replace aging infrastructure, achieve compliance with ADA, improve energy efficiency, and relocates the tower above the 100‐year flood stage. | $4,500,000 |
MP | Saipan | Francisco C. Ada/Saipan International Airport | GSN | This project will fund the reconstruction of the commuter terminal access road including new signage and markings. | $1,900,000 |
Mississippi | Starkville | George M. Bryan Airport | STF | This award funds a portion of a project to construct a new 9,850 square feet passenger terminal and associated utilities for charter and business passengers. | $4,500,000 |
Montana | Kalispell | Glacier Park International Airport | GPI | This project funds a portion of a phased expansion and modernization of an outdated and undersized terminal building. This project will expand the existing terminal by adding a new gate, passenger screening space and restrooms; and increasing hold room space and the bag claim area. | $7,300,000 |
North Carolina | Asheville | Asheville Regional Airport | AVL | This award funds a portion of the airport's Terminal Modernization and Expansion Project (PHASE 1 ‐ Terminal Construction). This project will replace the existing 61 year old terminal with new and expanded facility. It will expand the existing 115,000 square feet terminal with five gates to a 275,000 square feet terminal with twelve, Passenger Boarding Bridge equipped gates. The terminal modernization and expansion program is scheduled to be completed in three phases. | $10,000,000 |
North Carolina | Asheville | Asheville Regional Airport | AVL | This award funds a portion of the relocation and replacement of the existing 61 year old airport traffic control tower as part of the airport's terminal modernization and expansion program. | $10,000,000 |
North Carolina | Charlotte | Charlotte Douglas International Airport | CLT | This award funds a portion of the rehabilitation of the 120,000 square feet Concourse E, including updates to hold rooms, restrooms, and circulation areas. These updates will increase passenger capacity, meet ADA compliance, and enhance energy efficiency. | $32,000,000 |
North Carolina | New Bern | Coastal Carolina Regional Airport | EWN | This award funds a portion of terminal expansion and improvements to include the addition of two passenger boarding bridges, expansion of hold rooms, improvements to passenger and baggage screening and handling areas, and upgrades to facilitate the post 9/11 passenger and baggage screening requirements. | $5,000,000 |
North Dakota | Ashley | Ashley Municipal Airport | ASY | This award funds a project to construct a new 500 square feet general aviation terminal building for passengers and flight crews. The terminal will include a waiting area, flight planning and restrooms that are needed for this rural airport. | $950,000 |
North Dakota | Rugby | Rugby Municipal Airport | RUG | This award funds a project to reconstruct a 500 square feet General Aviation terminal building. The new modern facility will meet current standards and ADA requirements, be energy efficient, and meet the current and future passenger demand at the airport. | $500,000 |
Nebraska | Omaha | Eppley Airfield | OMA | The project is part of a Terminal Modernization Program (TMP), which includes additional aircraft gates, consolidating security screening and baggage handling systems and a central utility plant. This project (Phase 4 of the TMP) will construct a new 7‐lane terminal drop‐off area with full canopy and improve curb areas for ADA access and public transportation. | $10,000,000 |
New Hampshire | Portsmouth | Portsmouth International Airport at Pease | PSM | This award funds a terminal arrivals area expansion project. This includes expanding the public portion of the existing domestic bag claim arrivals hall, replacing the electric service, and redesigning the entrance and exit. | $7,000,000 |
New Jersey | Atlantic City | Atlantic City International Airport | ACY | This project replaces two existing passenger loading bridges that are beyond their useful life. | $4,800,000 |
New Mexico | Albuquerque | Albuquerque International Sunport | ABQ | This award will provide funding to refurbish at least 7 and up to 14 passenger boarding bridges and ground power units that have reached the end of their useful life. The refurbished bridges and new GPUs will increase accessibility, energy efficiency, and operational efficiency. | $7,000,000 |
Nevada | Las Vegas | Harry Reid International Airport | LAS | This project will fund baggage system upgrades in Terminals 1 and 3. Terminal 1 upgrades include new conveyors, carousels, and standby power systems. Terminal 3 upgrades include new control system compatible with Terminal 1 system upgrades. The project will enhance the capacity, security, reliability, energy efficiency and sustainability of the baggage handling system by replacing aging infrastructure. | $31,000,000 |
New York | Albany | Albany International Airport | ALB | This project rehabilitates the sponsor owned Airport Traffic Control Tower (ATCT) including existing mechanical, electrical, and HVAC building systems that have reached their useful life. The project will improve energy efficiency and bring the systems up to current standards | $2,000,000 |
New York | Binghamton | Greater Binghamton Airport | BGM | This project involves a renovation of the passenger terminal and the associated vehicle approach. The project funds a portion of the improvements to reconstruct the passenger hold room, replaces the aging HVAC equipment with reliable, energy efficient units, installs two passenger boarding bridges and expands the exterior canopy. | $7,000,000 |
New York | Buffalo | Buffalo Niagara International Airport | BUF | This project funds a portion of the rehabilitation of the aging terminal HVAC system. The renovations will enhance air quality and reduce greenhouse gas emissions. | $7,000,000 |
New York | Syracuse | Syracuse Regional Airport Authority | SYR | The Airport has started a sustainability initiative to increase energy efficiency and cut emissions of the terminal building. This project replaces the terminal HVAC system, windows, and siding with more energy efficient materials. | $8,600,000 |
Ohio | Cleveland | Cleveland Hopkins International Airport | CLE | This award funds a portion of a restroom renovation program to include the replacement of 25+ year old fixtures, aging appurtenances, and accessories in 13 airport terminal restrooms to high efficiency equipment. The new restrooms will meet environmental and ADA standards, and expand capacity. | $1,600,000 |
Ohio | Cleveland | Cleveland Hopkins International Airport | CLE | This award funds a portion of a project to rehabilitate and resurface approximately 2,100 feet of the public transportation tunnel membrane from downtown Cleveland to the Airport terminal building. The work will be comprised of rehabilitating wall surfaces, replacing the tunnel ceiling, and waterproof membrane in the tunnel tramway, structural repairs, and installation of a new drainage system. | $1,600,000 |
Ohio | Put‐In‐Bay | Put‐In‐Bay Airport | 3W2 | This award funds a portion of a project to replace the existing 55+ year old terminal building. The new modern terminal building will be approximately 2,500 square feet, single‐story building to include a public area, baggage room, mechanical room, and two restrooms. | $1,900,000 |
Oklahoma | Lawton | Lawton‐Fort Sill Regional Airport | LAW | The terminal modernization and expansion project includes a building expansion with a new baggage claim and meeter‐greeter areas, a new and expanded security checkpoint and hold room expansion that accommodates two airline gates. This award will provide funding to complete the final phase, which includes an expanded airline counter, office spaces, conveyor systems for departures, a passenger boarding bridge, and curbside area updates. | $4,379,131 |
Oklahoma | Oklahoma City | Will Rogers World Airport | OKC | The airport is replacing 17 Passenger Boarding Bridges which have exceeded their useful life. This award will fund 6 replacement PBBs with accessible and more energy efficient systems. | $4,500,000 |
Oregon | Portland | Portland International Airport | PDX | This project will convert the heating system at the PDX terminal from boilers fueled by fossil fuels to an electric‐powered heat pump. The heat pump will extract heat from an underground aquifer for heating and reject excess heat back into the aquifer for cooling. This project will significantly improve energy efficiency, reduce greenhouse gas emissions and harmful pollutants, create job opportunities, and strengthen climate resilience for this critical facility. | $6,000,000 |
Pennsylvania | Harrisburg | Harrisburg International Airport | MDT | This project funds a portion of the replacement of the baggage handling system with energy efficient components. | $5,500,000 |
Pennsylvania | Philadelphia | Philadelphia International Airport | PHL | The Restroom Renovation Program (RRP) will provide 13,000SF of additional restroom space and 35 more stalls throughout the terminals. This project funds a portion of phases 5 through 9 of the RRP including renovation and new construction of terminal restrooms, adult assisted care, mother's rooms and Service Animal Relief Areas (SARAs). | $15,000,000 |
Pennsylvania | Philadelphia | Philadelphia International Airport | PHL | This project funds a portion of the Terminal Energy Optimization Program (TEOP) which includes replacing/upgrading Pre‐Conditions Air (PCA) units and Ground Power Units (GPUs) at 25 gates, terminal/roadway lighting, and HVAC upgrades. | $15,000,000 |
Pennsylvania | Pittsburgh | Pittsburgh International Airport (PIT) | PIT | The Terminal Modernization Program (TMP) is the construction of a new 700,000 square feet landside terminal adjacent to the existing airside terminal. This project funds a portion of phase 2 of this 3 phased program, which includes a new baggage handling system, and elevators and escalators. | $3,500,000 |
Puerto Rico | Aguadilla | Rafael Hernandez Airport | BQN | This award funds a portion of a project to rehabilitate the existing 1942 era commercial terminal building, which is a modified aircraft hangar. It will add a second level departure hall with four contact gates for a mix of narrow‐ and wide‐ body aircraft, and construct a 12,000 square feet Customs and Border Protection (CBP) facility to handle international arrivals. | $6,000,000 |
South Carolina | Columbia | Columbia Metropolitan Airport | CAE | This project expands the terminal 5,400 square feet. This award funds a portion of expansion of the passenger security screening checkpoint by adding a fourth screening lane and bringing the checkpoint up to current TSA standards. | $5,000,000 |
South Carolina | Lancaster | Lancaster County Airport ‐ McWhirter Field | LKR | This award funds a portion of the replacement of the 44 year old facility with a new 5,200 square feet general aviation terminal building that meets existing and future demand. | $3,000,000 |
South Dakota | Rapid City | Rapid City Regional Airport | RAP | This award funds a portion of a multi‐phased rehabilitation and expansion of the existing passenger terminal. This project consists of the expansion of the baggage makeup area to support baggage carousels, relocation of TSA checkpoint to accommodate capacity, and expansion/remodeling of the ticketing area to allow additional passenger queuing. | $10,900,000 |
Tennessee | Memphis | Memphis International Airport | MEM | This award funds a portion of Phase 2 of the Terminal Modernization program to modernize the landside terminal by reconfiguring vertical circulation and ticket counters; installing common use ticketing technology and a fire suppression system; expanding the passenger security screening checkpoint queuing area; upgrading the buildings seismic resistance and the mechanical, electrical and plumbing systems; and replacing the window glazing. | $14,800,000 |
Tennessee | Millington | Charles W. Baker Airport | 2M8 | This award funds a portion of a project to construct a new general aviation terminal building. The new modern facility will meet ADA and seismic building standards, have energy efficient features, and meet the current demand at the airport. | $1,000,000 |
Tennessee | Nashville | Nashville International Airport | BNA | The Terminal Access Roadway Improvements (TARI) project is a reconfiguration of BNA's primary access roadway. The project will lengthen and widen the road, enhance safety, and improve wayfinding signage. This award would fund a portion of the construction cost of Phase 2, which includes grading, drainage, and utilities relocation. | $7,000,000 |
Texas | Fort Worth | Dallas‐Fort Worth International Airport | DFW | This award funds a portion of the Terminal D Energy Efficiency Enhancement program that replaces aging infrastructure with modern systems that will significantly improve energy efficiency and reduce NOx emissions. This project includes the replacement of the aging HVAC system, installation of dimmable smart glass in terminal windows, and eco‐friendly roof replacement. | $25,000,000 |
Texas | Fort Worth | Dallas‐Fort Worth International Airport | DFW | This award funds the second phase of the installation of the Airport’s Zero Carbon Electric Central Utility Plant (eCUP) that will be powered 100% by renewable energy. The eCUP will position DFW to achieve its target of net‐zero carbon emissions by 2030, providing the airport with uninterrupted redundant service. | $10,000,000 |
Texas | Houston | George Bush Intercontinental Airport | IAH | This award funds of a portion of the IAH Terminal Efficiency Project, which will replace or rehabilitate aged public restrooms, terminal entrance vestibules, lighting systems, escalators, elevators, moving sidewalks, and HVAC systems. | $9,600,000 |
Texas | Killeen | Killeen‐Fort Hood Regional Airport | GRK | This award funds the airport's retrofits for terminal lighting and adds pedestrian walkway solar canopy. This project improves passenger access, reduces the carbon footprint, and increases resiliency. | $5,000,000 |
Texas | Lubbock | Lubbock Preston Smith International Airport | LBB | This awards funds the design and construction services to replace the terminal electrical distribution system and the standby power system, as well as installs electrical infrastructure to support the recently expanded terminal, future electric vehicle charging demands, and complete the existing grounding system. | $4,750,000 |
Texas | McAllen | McAllen International Airport | MFE | This award funds the upgrade of the terminal HVAC mechanical controls, and lighting to be more energy efficient, improve sustainability, and reduce overall operating expenses. | $1,980,000 |
Texas | San Antonio | San Antonio International Airport | SAT | This award will fund a portion of Phase 1 for the construction of the Ground Load Facility (GLF) at Terminal A which includes adding 5 new gates, hold rooms and other passenger facilities. This awards supports new flexible, common‐use gates that accommodate domestic and international operations with an integrated Federal Inspection Station for international arrivals. | $20,000,000 |
Utah | Salt Lake City | Salt Lake City International Airport | SLC | The New SLC is a phased Terminal and North Concourse Redevelopment Program which replaces aging and capacity constrained facilities. This award funds a portion of Phase 4 of the New SLC includes 16 contact gates as well as up to 5 permanent hardstand positions in Concourse B. | $29,000,000 |
Virginia | Dulles | Washington Dulles International Airport | IAD | The Tier‐2 Concourse (East) 14‐gate project will serve aircraft via loading bridges rather than existing ground loading and increases holdroom size. The proposed 400,000 SF project connects directly to our Aerotrain and indirectly to the public Metrorail. This project will replace existing ground loading positions with 14 loading bridges on the Tier‐2 Concourse. | $20,000,000 |
Virginia | Highland Springs | Richmond International Airport | RIC | This award funds a portion of a project to replace 21 passenger loading bridges that are beyond their useful life. | $4,000,000 |
Virginia | Norfolk | Norfolk International Airport | ORF | This project will construct a people mover on the pedestrian bridge connecting the departures and arrivals terminal buildings. | $5,400,000 |
Vermont | Burlington | Burlington International Airport | BTV | The Airport is constructing a new 2 level 45,000 square feet South terminal. This new terminal will include 5 new aircraft gates; 4 new passenger boarding bridges, and new passenger circulation and holdrooms. This award funds the design portion of the project. | $2,090,000 |
Washington | Pullman | Pullman‐Moscow Regional Airport | PUW | The airport is currently constructing a new terminal. This project will provide for a third gate and boarding bridge in the new terminal which will provide additional boarding capacity and decreased wait times. | $6,365,000 |
Washington | Seattle | Seattle‐Tacoma International Airport | SEA | This project will relocate Security Checkpoint 1 from the ticketing level to the lower baggage claim level, which will provide additional screening capacity and improved wait times. The project will include energy efficient upgrades and will meet or exceed all applicable ADA standards. | $16,000,000 |
Washington | Spokane | Spokane International Airport | GEG | This project will provide for the final phase of the Concourse C ‐ West expansion portion of the terminal renovation and expansion (TREX) program. The phase will finalize construction of three additional gates by providing finishes (acoustical ceilings, flooring, millwork, doors, hardware) and elevators. When complete, TREX will accommodate both existing and future passenger demand, provide a LEED certified facility with numerous energy efficient upgrades, an upgraded baggage system, and will meet all applicable ADA requirements. | $15,000,000 |
Wisconsin | Milwaukee | General Mitchell International Airport | MKE | This project will replace the flat roof areas over Concourse D at MKE that have reached their useful life. The scope of the project includes both design and construction for removal of existing roof material and installation of a new roof. | $5,100,000 |
West Virginia | Beckley | Raleigh County Memorial Airport | BKW | This project expands the terminal 1,630 SF to accommodate a 50 seat hold room, adds accessible restrooms, and includes several sustainable design concepts to promote energy efficiency. This project funds a portion of the construction. | $1,000,000 |
West Virginia | Charleston | West Virginia International Yeager Airport | CRW | The Airport terminal needs a series of projects to upgrade and extend the useful life of a 1950s building and improve ADA compliance. This project funds a portion of the construction of the terminal roof replacement that has exceeded its useful life. | $1,000,000 |
STATE | CITY | AIRPORT NAME | AIRPORT LOCID | REGIONAL — PROJECT DESCRIPTION | FINAL APPROVED AMOUNT |
The ten international airports which serve the greater metropolitan areas of the cities were approved of the most funds for 2023 in the following order:
- Chicago — 50 million dollars
- Orlando — 49 million dollars
- Baltimore — 38 million dollars
- Charlotte — 32 million dollars
- Los Angeles — 31 million dollars
- San Francisco — 31 million dollars
- Las Vegas — 31 million dollars
- Burbank — 30 million dollars
- Salt Lake City – 29 million dollars
- Fort Worth — 25 million dollars
Interactive List of 85 Airports Which Were Approved For Funding 2022
An interactive list of the 85 airports which have been approved for financial aid from the first round of funding for the Airport Terminals Program from the bipartisan infrastructure law was custom created for your convenience.
STATE | CITY | AIRPORT NAME | AIRPORT LOCID | REGIONAL — PROJECT DESCRIPTION | FINAL APPROVED AMOUNT |
---|---|---|---|---|---|
Alaska | Anchorage | Ted Stevens Anchorage International Airport | ANC | The existing bridge has outlived its useful life. The new passenger boarding bridge will increase passenger capacity and improve energy efficiency. | $2,432,000 |
Alabama | Huntsville | Huntsville Intl-Carl T Jones Fld | HSV | The grant will allow for construction of a new terminal facility. Other improvments include expansion of existing terminal public areas, family restrooms, lactation rooms and a Service Animal Relief Area. These enhancements to the terminal will improve energy efficieny and achieve Americans with Disabilities Act (ADA) compliance for individuals with access and functional needs. | $10,000,000 |
Alabama | Demopolis | Demopolis Regional Airport | DYA | The construction of a new General Aviation terminal building will replace the existing 47-year-old structure. The new terminal will be more energy efficient, increase the passenger capacity and be more accessibile for individuals with access and functional needs. | $1,260,000 |
Arkansas | Fayetteville/Springda le/Rogers | Northwest Arkansas National Airport (XNA) | XNA | Funding will support significant upgrades to increase energy efficiency and infrastructure for individuals with access and functional needs. Terminal updates will focus on the expansion of the terminal, adding an upper level walkway bridge, replacing and adding escalators, and updating baggage system. | $13,000,000 |
Arkansas | Texarkana | Texarkana Regional Airport | TXK | Funding will assure the completion of the terminal expansion and two new passenger boarding bridges. The terminal and new passenger bridges increase passenger capacity and improve accessibility for individuals with access and functional needs. | $5,000,000 |
Arizona | Phoenix | Phoenix-Mesa Gateway Airport | IWA | The modernization consists of updating and expanding the existing terminal to replace the temporary 4-gate facility with a permanent 5-gate. The new terminal facility will improve energy efficiency and achieve Americans with Disabilities Act (ADA) compliance for individuals with access and functional needs. | $14,400,000 |
California | Los Angeles | Los Angeles International | LAX | The terminal roadways will be reconfigured and repaved. The project will also include the reconfiguring and modernization of the entrance to the central terminal area parking. These updates will increase passenger capacity for everyone including those with access and functional needs. | $50,000,000 |
California | San Diego | San Diego International Airport | SAN | The existing Terminal 1 facility will be demolished and construction on new terminal facility with 19 gates will begin. In addition to the new terminal facility, additional energy efficiency improvements will be made to the airport. | $24,000,000 |
California | San Jose | Norman Y. Mineta San José International Airport | SJC | The terminal facilities will be updated improving accessibility throughout the terminal and bringing it into compliance with the American with Disability Act (ADA). These updates will increase passenger capacity for everyone including those with access and functional needs. | $10,000,000 |
California | Long Beach | Long Beach Airport | LGB | The terminal roadways will be reconfigured and repaved. The project will also include the realignment of the terminal loop. These upgrades will alllow for an increase in passenger capacity and improve Americans with Disabilities Act (ADA) compliance for indviduals with access and functional needs. | $10,600,000 |
Colorado | Denver | Denver International Airport | DEN | This project includes improvements to the terminal facility including replacing the baggage handling system. The new system will improve energy efficiency and will accommodate increased capacity to 100M annual passengers. | $60,000,000 |
Colorado | Durango | Durango-La Plata County Airport | DRO | The grant funds the first phase of the terminal rehabilitation program. This includes an additional 3,300 sqft of post screening area and the addition of one new gate for increased passenger capacity. The enhancements further improve energy efficiency, and increases accessibility for individuals with access and functional needs. | $3,200,000 |
Connecticut | Windsor Locks | Bradley International Airport | BDL | The existing checked baggage inspection system (CBIS) is located in the ticket counter area which limits capacity, creates passenger congestion and delays. The funding will be used for terminal expansion to provide an in-line CBIS and implementation of an airport wide baggage handling system with upgrades. Additionally energy efficient updates throughout the terminal include the installation of elevators, upgraded HVAC system and new Americans with Disabilities Act (ADA) compliant restrooms. | $20,000,000 |
Florida | Orlando | Orlando International Airport | MCO | The South Terminal C expansion includes the addition of 4 gates with 8 loading bridges to the terminal facility. The project increases passenger capacity, improves Americans with Disabilities Act (ADA) compliant facilities, and achieves LEED certification. | $50,000,000 |
Florida | Sarasota/Bradenton | Sarasota Bradenton International Airport | SRQ | A new Concourse Ground Boarding Facility will be constrcuted. The new Concourse A Ground Boarding Facility will add five new gates and hold rooms, add four security checkpoint lanes, and replace the existing two-chiller Central Energy Plant (CEP). Funding will also be used to improve the existing Concourse B. Improvements will include expanding holdrooms, adding escalators, modifying gate entrances, and upgrading power and communications equipment. The project will increase passenger capacity, improves accessibility for individuals with access and functional needs, and increases energy efficiency. | $10,000,000 |
Florida | Gainesville | Gainesville Regional Airport | GNV | Improvements to the Multi-modal Ground Transport Facility include updated lighted, accessible, covered walkways to the commercial airline terminal, a covered passenger waiting area, accessible restrooms, and queing lanes for taxis and city busses arriving and departing the terminal. These improvements will reduce curbside congestion and improve Americans with Disabilities Act (ADA) compliance for individuals with access and functional needs. | $1,677,250 |
Georgia | Atlanta | Hartsfield-Jackson Atlanta International Airport | ATL | This project will update and modernize the 40-year-old Concourse D. The rehabilitation project also includes enlarging hold rooms, restrooms, and the central corridor. These updates will increase passenger capacity, improve Americans with Disabilities Act (ADA) compliance for individuals with access and functional needs, and achieve Leadership in Energy and Environmental Design (LEED) gold certification. | $40,000,000 |
Hawaii | Honolulu | Daniel K. Inouye International Airport | HNL | The terminal roadways will be reconfigured and repaved. In addition, select updates to the drainage and lighting on select terminal floors of the Ewa and Diamond Head Concourses will be made. These upgrades will alllow for an increaseenergy efficiency and improve Americans with Disabilities Act (ADA) compliance for indviduals with access and functional needs. | $10,000,000 |
Iowa | Cedar Rapids | Eastern Iowa Airport (CID) | CID | The passenger terminal will be expanded with the addition of four passenger gates. This will complete the airport's terminal modernization program. The additional gates not only increases passenger capacity but will improve accessibility for individuals with access and functional needs and improves energy efficiency. | $20,415,727 |
Iowa | Des Moines | Des Moines International Airport | DSM | The fuding will allow for the planning and design of a 4-phase new terminal project. Phase 1 includes the site work, officially kicking off the construction of the new terminal. The new terminal will improve enery efficiency, improve accessibility for individuals with access and functional needs and create jobs during the construction of the terminal. | $5,000,000 |
Iowa | Washington | Washington Municipal Airport (AWG) | AWG | A new solar power system will be installed in the General Aviation terminal. In addition to the solar power system, associated electrical efficiency enhancements will be made throughout the terminal. These updates will further improve the energy efficiency of the terminal. | $129,675 |
Iowa | Council Bluffs | Council Bluffs Municipal Airport | CBF | A new elevator will be installed in the General Aviation terminal. The elevator will increase Americans with Disabilities Act (ADA) compliance and accessibility to the second floor for indviduals with access and functional needs. | $112,500 |
Iowa | Dubuque | Dubuque Regional Airport | DBQ | A new solar power system will be installed in the passenger terminal. In addition to the solar power system, associated electrical efficiency enhancements will be made throughout the commercial passenger terminal. These updates will further improve the energy efficiency of the terminal. | $1,346,112 |
Idaho | Boise | Boise Airport | BOI | Improvements to the terminal building include replacing the aging boiler with a newer more energy efficient boiler. Additionally, new more energy efficient skylights will be installed to provide a natural light source for the terminal. These improvement further support Boise's clean energy goal. | $960,000 |
Illinois | Carbondale/Murphysboro | Southern Illinois Airport Authority | MDH | The existing terminal building does not meet Americans with Disabilities Act (ADA) compliance. The project will provide the funding required to complete the construction of a new terminal building that will increase passenger capacity, improve accessibility for individuals with access and functional needs and improve energy efficiency. Additionally, the new terminal will create jobs during the construction as well as once the terminal is operational. | $1,039,404 |
Illinois | Peoria | General Wayne A. Downing Peoria International Airport | PIA | The existing Air Traffic Control Tower (ATCT) is over 60 years old and does not meet Americans with Disabilities Act (ADA) requirements. The construction of a new tower will meet all current building codes including ADA requirements to provide a safe working environment for all employees. Additionally, the new ATCT tower will utilize modern, energy efficient HVAC systems and lighting. | $15,000,000 |
Indiana | Fort Wayne | Fort Wayne International Airport | FWA | The existing terminal is over 30 years old with inefficient HVAC units and insulation. Additionally, the existing terminal building does not provide adequate space for passenger waiting and boarding areas. The terminal improvements will modernize the energy efficient HVAC units, insulation, lighting and improve access for passengers including individuals with access and functional needs. The expansion project will improve safety and operations by increasing taxiway separation to the terminal. | $13,800,000 |
Indiana | Evansville | Evansville Regional Airport | EVV | Improvements to the existing terminal facility include replacing the outdated HVAC equipment, lighting and passenger access systems. The existing systems are past their useful life and require frequent maintenance. The new HVAC, lighting and passenger access systems will be energy efficient, increase passenger access and improve accessibility for individuals with access and functional needs. | $3,420,000 |
Kansas | Augusta | Augusta Municipal Airport | 3AU | This project removes and installs a new HVAC system in the General Aviation terminal building. The new HVAC system will be energy efficient. | $36,000 |
Kansas | Topeka | Topeka Regional Airport | FOE | The existing passenger loading bridge, originally acquired in 1985, has exceeded its useful life. It is causing distresses at the terminal building connection, requiring foundation improvements at the building connection point. A new loading bridge will increase passenger capacity and ensure Americans with Disabilities Act (ADA) compliance for individuals with access and functional needs. | $1,900,000 |
Kansas | Lawrence | Lawrence Regional Airport | LWC | The project renovates the General Aviation terminal building that was originally constructed in 1985. Improvement to the terminal facility include new roofing, HVAC, windows, and various exterior refurbishments. The renovations to the terminal building will be energy efficient and create jobs during the renovation project. | $1,075,124 |
Kansas | Topeka | Philip Billard Municipal Airport | TOP | The existing general aviation terminal building, originally constructed in the 1950s, has exceeded its useful life. The new terminal facility will increase passenger capacity and ensure Americans with Disabilities Act (ADA) compliance for individuals with access and functional needs. | $3,800,000 |
Kentucky | Henderson | Henderson City-County Airport | EHR | The roof of the existing terminal building has exceeded its useful life. The funding will help with replacing the aging roof that is showing signs of distress. | $247,950 |
Louisiana | Baton Rouge | Baton Rouge Metropolitan Airport | BTR | Two passenger boarding bridges will be replaced with more accessible and energy efficent bridges. The updated bridges will increase reliability, improve passenger capacity and ensure Americans with Disabilities Act (ADA) compliance for individuals with access and functional needs. | $5,200,000 |
Louisiana | Lake Charles | Lake Charles Regional Airport | LCH | Two passenger boarding bridges will be replaced with more accessible and energy efficent bridges. The updated bridges will increase reliability improving passenger capacity and ensuring Americans with Disabilities Act (ADA) compliance for individuals with access and functional needs. | $2,500,000 |
Massachusetts | Boston | General Edward Lawrence Logan International Airport | BOS | The pavement for the roadways have begun showing signs of deterioration. The grants will allow for the replacement of the aging infrastructure. Renovations to Terminal E include replacing the HVAC system, expanding the baggage claim area to accommodate gate expansions, and rehabilitating the existing ticket counter area, gates and jet bridges. These improvements will increase energy efficiencies throughout the terminal and assist the Massachusetts Port Authority in meeting its goal of Gold Leadership in Energy and Environmental Design (LEED) certification. | $62,000,000 |
Maine | Dexter | Dexter Regional Airport | 1B0 | The existing terminal building is beyond it useful life and does not meet current standards or needs for a General Aviation terminal building. A new 800 square foot terminal building will replace the existing 50 year old 200 square feet terminal building. The new terminal building will improve energy efficiency and increase accessibility for individuals with access and functional needs. | $760,000 |
Maine | Bangor | Bangor International Airport | BGR | Terminal renovations and expansion will include replacing the HVAC system, replacement of one ground level boarding gate, construction of a connector between the two terminal buildings and the expansion of the passenger security screening checkpoint. The construction of the connector is to provide the air carriers increased flexibility and opportunities to expand service by providing access to gates in both terminal buildings. | $14,200,000 |
Michigan | Detroit | Detroit Metropolitan Wayne County Airport | DTW | Funding will allow for the replacement of the passenger boarding bridges that improve energy efficiency and enhance accessibility for individuals with access and functional needs. Existing public restrooms throughout the airport will be updated to enhance accessibility for individuals with access and functional needs. The restroom upgrades will also inlude the addition of gender inclusive restrooms. All restroom fixtures will be replaced with energy efficient fixtures. In addition, new baggage claim belts will be installed to improve the baggage handling system and improve energy efficiency. | $49,600,000 |
Michigan | Grand Rapids | Gerald R. Ford International Airport | GRR | As part of the ongoing terminal gate expansion project, funding will be used to install eight new passenger boarding bridges. The new boarding bridges will provide enhanced accessibility for all passengers by eliminating the need for ground-level loading. These bridges will also enhance energy efficiency with pre-conditioned air and auxiliary power. | $8,687,870 |
Michigan | Flint | Bishop International Airport | FNT | The exisiting terminal roof has reached the end of its useful life and will be replaced with energy efficient materials, including improved insulation. The new roof will decrease heating and cooling needs and in turn, reduce energy consumption. | $3,500,000 |
Minnesota | Minneapolis | Minneapolis-St. Paul International Airport | MSP | This project will make several improvements to the terminals. Projects include the addition of five new boarding bridges and one relocated bridge. Additional projects include replacing electrical substations that serve critical areas of the baggage system along with the north security checkpoint and airport police area. Funding will allow for modified walkways, ramps, and slopes to better utilize space and meet Americans with Disabilities Act (ADA) requirements. | $21,300,000 |
Minnesota | Bemidji | Bemidji Regional Airport | BJI | This project will reconfigure and expand security screening area at the airport. These updates will increase capacity and passenger flow at the security checkpoint. | $95,000 |
Minnesota | Preston | Fillmore County Airport | FKA | This project will construct new general aviation terminal to meet Americans with Disabilities Act (ADA) requirements and Leadership in Energy and Environmental Design (LEED) certification. | $950,000 |
Minnesota | Glencoe | Glencoe Municipal Airport | GYL | This project will construct a new General Aviation terminal to meet Americans with Disabilities Act (ADA) requirements. The new terminal building will use energy efficient solutions such as LED lights and water conservation fixtures. | $712,500 |
Missouri | Hannibal | Hannibal Regional Airport | HAE | This project will repair the leaking roof and damaged building infrastructure. The rehabiliation project will help extend the useful life of the terminal facility. | $285,000 |
Missouri | St. Joseph | Rosecrans Memorial Airport | STJ | A new passenger terminal will be constructed to replace the exisiting terminal. The new terminal will be constructed above the 100-year flood zone to mitigate future flooding. Additionally, the terminal will achieve compliance with the Americans with Disabilities Act (ADA) and improve energy efficiency. | $1,980,000 |
Missouri | Fort Leonard Wood | Waynesville-Saint Robert Regional Airport | TBN | This project constructs a new commercial passenger terminal facility to meet increasing capacity and passenger access. The new terminal will improve airfield safety by separating military and civilian areas and activities. | $3,000,000 |
Mississippi | Columbus/West Point/Starkville | Golden Triangle Regional Airport | GTR | This project renovates the existing terminal to provide jet bridge access for larger aircraft. The project adds a second floor on the terminal to improve Americans with Disabilities Act (ADA) accessibility and airport capacity. | $11,352,358 |
Montana | Missoula | Missoula Montana Airport | MSO | This project will fund Phase 2 of the airports terminal replacement. Construction of the new terminal building will provide added capacity for increased demand, while also improving energy efficiency and accessibility for individuals with access and functional needs. | $11,000,000 |
Montana | West Yellowstone | Yellowstone Airport | WYS | The existing terminal is outdated and does not today's standards. This project adds a new terminal with adequate space for ticketing, hold rooms and will meet Americans with Disabilities Act (ADA) requirements. | $10,000,000 |
North Carolina | Asheville | Asheville Regional Airport | AVL | This project replaces an existing 61-year-old Air Traffic Control Tower with a new, expanded facility. The project will enable increased terminal capacity, replace aging and obsolete infrastructure, improve airfield safety, upgrade the facility to Americans with Disabilities Act (ADA) standards, and increase energy efficiency. | $15,000,000 |
North Dakota | Mott | Mott Municipal Airport | 3P3 | The construction of a new General Aviation terminal building will replace the existing structure that hos reached its useful life. The new terminal will be more energy efficient and more accessibile for individuals with access and functional needs. | $380,000 |
Nebraska | Omaha | Eppley Airfield | OMA | This project will construct a new terminal drop-off area and full canopy and additional aircraft gates. Additional updated include consolidating security screening and baggage handling systems and a central utility plant. The project also includes improved curb areas for Americans with Disabilities Act (ADA) access and public transportation. | $20,000,000 |
Nebraska | Lincoln | Lincoln Airport | LNK | This project replaces the existing Lincoln terminal cooling towers, fans, internal exhaust decks, control equipment and associated plumbing. This project's overall aim is to resolve passenger and baggage screening area constraints and to rebuild the airline areas to allow for more flexible and competitive commercial air service opportunities. | $850,000 |
New Hampshire | Manchester | Manchester-Boston Regional Airport | MHT | This project will replace approximately 16,000 square feet of the existing glass canopy roofing and wall system that was originally installed in 1993 over the ticketing and bag claim areas, main escalators and the passenger security screening checkpoint. The higher performing panel system will improve natural lighting in the terminal reducing the dependency of artificial lighting and reduce the heating of these areas, which adds energy efficiency. | $4,116,190 |
New Mexico | Albuquerque | Albuquerque International Sunport | ABQ | Funding supports new mechanical, electric, and lighting systems for increased efficiency, as well as new materials and connections to enhance Americans with Disabilities Act (ADA) access. | $7,000,000 |
New York | Islip and New York | Long Island MacArthur Airport | ISP | This project upgrades the Main Terminal Building utilities and fire and life safety systems to comply with current building codes and provide greater energy efficiency. The project includes the installation of new 800 kVA generator to ensure continuous and efficient operation of the Main Terminal Building and Maintenance Building. | $14,110,000 |
New York | Rochester | Frederick Douglass - Greater Rochester International Airport | ROC | This project replaces passenger boarding bridges with new state-of-the-art and energy efficient ones. | $5,225,000 |
Ohio | Versailles | Darke County Airport | VES | This project will construct a new terminal building to comply with accessibility requirements and provided enhanced energy efficiency by replacing the outdated HVAC system with a new higher efficiency unit which will reduce overall energy consumption at the airport. | $1,350,000 |
Ohio | Newark | Newark Heath Airport | VTA | This project will construct a new terminal building to comply with accessibility requirements and provide enhanced energy efficiency by replacing the outdated HVAC system, which will reduce overall energy consumption at the airport. | $2,385,000 |
Oklahoma | Oklahoma City | Will Rogers World Airport | OKC | This project will reduce idling cars in the terminal area, increase landside safety and Americans with Disabilities Act (ADA) access with new walkways from the terminal to air cargo facilities and employee parking lot. | $1,400,000 |
Oregon | Portland | Portland International Airport | PDX | This project will install a new heat pump replacing old chillers and boilers that are up to 50 years old. The new heat pump will reduce carbon emissions and provide an estimated 83% reduction in energy demand to heat and cool the building. This project will meet the goal of zero carbon emissions by 2050. | $18,400,000 |
Pennsylvania | Philadelphia | Philadelphia International Airport | PHL | This project is a continuation of the Restroom Renovation Program that will renovate 30 restrooms, construct two new restrooms, five lactation rooms, four service animal relief areas, 49 gender neutral restrooms, and three adult-assisted- care restrooms. This project will provide 13,000 square feet of additional restroom space and 35 more stalls throughout terminals featuring smart restroom and touchless technology that enhances sustainability. | $24,000,000 |
Pennsylvania | Pittsburgh | Pittsburgh International Airport (PIT) | PIT | This project will add a new 700,000 square-foot terminal next to the existing one. This will improve passenger security screening checkpoint, checked baggage inspection system, baggage handling equipment, U.S. Customs and Border Protection area and associated public spaces and support functions to meet the operational needs of the airport. | $20,000,000 |
Pennsylvania | Allentown | Lehigh Valley International Airport | ABE | This project adds four lanes to the security screening checkpoint to address capacity limitations and insufficient space to accommodate existing passenger volume and the necessary security screening equipment. | $5,000,000 |
South Dakota | Chamberlain | Chamberlain Municipal Airport | 9V9 | This project will replace an existing mobile home that is currently being used as a general aviation terminal. The existing facility does not meet Americans with Disabilities Act (ADA) requirement or the needs of the airport and will seek Leadership in Energy and Environmental Design (LEED) certification. | $855,000 |
Tennessee | Chattanooga | Chattanooga Metropolitan Airport | CHA | This is phase one of a terminal project that will add 26,779 square feet for two new gates, one expanded gate, new restrooms, and more space for passenger queuing, hold room and circulation areas. This phase will also add a lane for security screening and expand the terminal rotunda to provide adequate passenger queuing space. The project will increase terminal capacity, improve Americans with Disabilities Act (ADA) accessibility and increase energy efficiency. | $5,000,000 |
Tennessee | Crossville | Crossville Memorial Airport - Whitson Field | CSV | This project will bring the existing terminal building into compliance with Americans with Disabilities Act (ADA) standards by modernizing the roof and restrooms improving Americans with Disabilities Act (ADA) accessibility and energy efficiency. | $475,000 |
Texas | Dallas-Fort Worth | Dallas-Fort Worth International Airport | DFW | This project constructs a zero carbon electrical central utility plan, which will assist the airport's goal of net zero carbon emissions by 2030. Phase 1 will construct the facility and convert two of five terminals. Phase 2 will convert the remaining three terminals and on-site hotel. | $35,000,000 |
Texas | Houston | George Bush Intercontinental Airport | IAH | This project improves energy efficiencies, ticketing, security screening checkpoints, baggage systems, gates, modernizes curbside access and loading bridges. | $40,000,000 |
Texas | Austin | Austin Bergstrom International Airport | AUS | Funds will prepare airport for future growth by improving accessibility with hearing loops, wayfinding, and multi-lingual assistance, plus assistive care restrooms and Americans with Disabilities Act (ADA) compliance throughout. Grant will allow Leadership in Energy and Environmental Design (LEED) Silver goal projects including energy efficient systems, glass tinting, and green energy construction. | $15,000,000 |
Texas | Houston | William P. Hobby Airport | HOU | This project will add new gates and baggage systems. Americans with Disabilities Act (ADA) access will be improved with wheelchair turning clearances in restrooms, video relay services, animal-relief areas, hearing loops and sensory rooms as well as adult changing and mother’s rooms. Energy efficiency enhancements include new lighting, high-efficiency insulation and energy efficient glass in pursuit of Leadership in Energy and Environmental Design (LEED) Silver standards. | $3,600,000 |
Texas | El Paso | El Paso International Airport | ELP | This project replaces ceiling panels and adds energy efficient lighting as well as new passenger seating to provide device charging and improves Americans with Disabilities Act (ADA) access. | $5,000,000 |
Texas | Corpus Christi | Corpus Christi International Airport | CRP | This project will modernize restrooms to include mother’s rooms and service animal relief areas for Americans with Disabilities Act (ADA) compliance. Also, the project will modernize energy management systems including generators for heating and air conditioning to increase energy efficiency and add electric vehicle charging stations. | $1,800,000 |
Texas | Arlington | Arlington Municipal Airport | GKY | This project includes replacing aging HVAC systems with energy efficient and more reliable systems. | $540,000 |
Texas | Laredo | Laredo International Airport | LRD | These funds will add new security checkpoints in the airport. Additional concessions space will encourage airside and in- terminal jobs and competition. The project also includes construction of additional restrooms, service animal relief areas, and sensory room, improving Americans with Disabilities Act (ADA) compliance and accessibility. | $2,500,000 |
Virginia | Washington | Washington Dulles International Airport | IAD | Construction on a new 14 gate concourse will replace the existing temporary concourse constructed in 1999. The new two-tier concourse will increase passenger access, improve accessibility for indivuals with access and funtional needs and improve energy efficiency. | $49,600,000 |
Virginia | Richmond | Richmond International Airport | RIC | This project will renovate the facility to meet current federal standards for international passenger processing and meet Americans with Disabilities Act (ADA) requirements. Updates to the facility will improve energy efficiency and increase passenger capacity. | $665,000 |
Washington | Seattle | Seattle-Tacoma International Airport | SEA | This project will modernize restrooms to be Americans with Disabilities Act (ADA) compliant. Additional updates include low-flow fixtures and refillable water bottle stations, energy efficient lighting and three service-animal relief areas. | $10,000,000 |
Washington | Spokane | Spokane International Airport | GEG | Expansion of the Concourse C terminal will improve Americans with Disabilities Act (ADA) accessibility for individuals with access and functional needs and add other Leadership in Energy and Environmental Design (LEED) certified improvements. | $11,000,000 |
Washington | Pullman/Moscow | Pullman-Moscow Regional Airport | PUW | Construction of the new terminal building replaces the existing terminal originally built for smaller aircraft. The new terminal will accommodate larger aircraft that serve thei airport as well as the increase in passenger capacity. The new terminal will have improved energy efficiency and Americans with Disabilities Act (ADA) compliance. | $11,800,000 |
Wisconsin | Madison | Dane County Regional Airport - Truax Field | MSN | This project will resurface the pavement, install 400 new energy efficient LED street lights, improve public bus access and safety, improve signage and guidance and improve traffic movement efficiency that will reduce emissions. | $2,600,000 |
West Virginia | Clarksburg | North Central West Virginia Airport | CKB | A new 45,000-square-foot terminal building with two additional gates replaces the original terminal built in 1945. The new terminal project will increase passenger capacity. Additionally, the project will use Leadership in Energy and Environmental Design standards and provide full Americans with Disabilities Act (ADA) compliance. | $15,000,000 |
Wyoming | Jackson | Jackson Hole | JAC | This project increases passenger capacity by adding two new gates. Additionally, new geothermal heating for the terminal will increase its energy efficiency. | $8,000,000 |
STATE | CITY | AIRPORT NAME | AIRPORT LOCID | REGIONAL — PROJECT DESCRIPTION | FINAL APPROVED AMOUNT |
The ten international airports which serve the greater metropolitan areas of the cities were approved of the most funds for 2022 in the following order:
- Boston — 62 million dollars
- Denver — 60 million dollars
- Los Angeles — 50 million dollars
- Orlando — 50 million dollars
- Detroit — 49.6 million dollars
- District of Columbia — 49.6 million dollars
- Atlanta — 40 million dollars
- Houston — 40 million dollars
- Dallas – Fort Worth — 35 million dollars
- San Diego — 24 million dollars
Final Boarding Call
Many members of the Republican Party opposed the infrastructure bill because they were concerned that the legislation includes provisions which address issues that are not directly related to “hard” infrastructure — such as billions of dollars for climate change and increased access to broadband as two of many examples — as well as objecting to the costs, which would purportedly pave the way for additional deficit spending…
…but whether they are right or wrong to be concerned, a number of the projects on that list are indeed necessary for sorely needed upgrades at airports — as well as for roads, bridges, public transportation, and the electric power grid in general — and they will create thousands of jobs.
We shall eventually see whether the Infrastructure Investment and Jobs Act is the right vehicle in its present state to accomplish what needed to be done for years: upgrade critical infrastructure around the United States — but completion for many of the projects will take years.